|
|
|
|
May
19, 2006 |
For
Immediate Release |
AUDITOR
GENERAL’S REPORT REVEALS ANOTHER ADSCAM?
“How much was paid in commissions? Who got paid and
where did the money end up?”
OTTAWA
- Saskatchewan M.P. Garry Breitkreuz and long-time critic of the Liberal
gun registry couldn’t believe it when he read section 4.83 in the
Auditor General’s most recent report on the gun registry. “It
sounded so much like the sponsorship scandal, I almost fell out of my
chair,” exclaimed Breitkreuz. “Mrs. Fraser’s
report tells us that contracts were awarded through a non-competitive
process, lacked due regard to economy, added two additional commissions
and increased costs by an average of 25 percent. Commissions for what?”
asked Breitkreuz. “How much was paid in commissions? Who got paid
and where did the money end up? This is exactly what happened in Adscam.”
Excerpt from
Chapter 4, point 4.83, page 120 of the Auditor General’s Report:
|
The
Information Technology Services Branch (ITSB). This
branch of Public Works and Government Services Canada (PWGSC) provides
IT professional services to departments through three master contracts
it has with IT consulting firms. These contracts were awarded
through a competitive procurement process. Client departments request
professional services from ITSB through a service agreement.
We found that in 11 cases, incumbent contractors who had been at the
Centre for several years remained there from 2004 to 2005 under ITSB
supply arrangements. We found evidence that the Centre asked ITSB
to provide its list of incumbent contractors to the IT consulting
firm under contract with ITSB, with the intention of continuing their
services. PWGSC officials said that they agreed to this practice because
the Centre told them that it needed the incumbents in order to meet
operational requirements. We also found documents showing that PWGSC
staff assured the Centre that it was procuring professional services
legitimately. In our opinion, because the individual task
authorizations were used to direct business to specified contractors,
the end result was a non-competitive process and did not meet
the objectives of the Treasury Board Contracting Policy. They also
lacked due regard to economy—for each incumbent, the Centre
paid ITSB, who paid the IT consulting firm, who, in many cases, paid
the sub-contractor, who finally paid the incumbent. Using ITSB
added two additional commissions to the cost of a consultant.
We noted that on average the cost to the Centre for each consultant
increased by about 25 percent under this supply arrangement.
[Emphasis added] |
The Auditor
General continues her revelations in point 4.85 that states:
|
We
also found specific cases in our sample of 147 contracts that did
not follow good contracting practices. Her report went
on to provide samples of these contracts and concluded: Several
fixed-price contracts were awarded to three contractors in 2001 and
2002 that, in some cases, had no measurable deliverable, and
no record of a deliverable product being received. The initial
value of each contract was below the $25,000 limit, but the final
values were much higher: $50,000, $107,000, and $319,431. We noted
that requests for the contractors' security clearance stated that
they would have no access to the work site. In these cases,
the Centre was the contracting authority. We will be reviewing
these contracts in greater detail. [Emphasis added] |
“Last November
I released documents showing five companies were burning up $527 million
in useless gun registry computer contracts. When the Auditor General finishes
digging into the firearms fiasco it could make Adscam look like small
potatoes and the Liberals look even worse than they do now. “What
will we call this one: Gunscam or Gungate?” wondered Breitkreuz.
-30-
Le 19 mai
2006 - LA VÉRIFICATRICE GÉNÉRALE AURAIT-ELLE DÉCOUVERT
UN NOUVEAU SCANDALE DE L’AMPLEUR DE CELUI DES COMMANDITES . . .
click
here
|